Grayslake High School District 127 North High School Expansion & Renovation

Client

Grayslake HSD 127

Architect

FGM Architects

Role

Construction Management

Through a competitive selection process, ICI was chosen as Grayslake High School District 127’s Construction Manager in the fall of 2012. Working with District architect, FGM Architects, ICI recently completed an addition and renovation to North High School.

Construction began in the summer of 2013. The two-story addition of approximately 11,000 SF makes way for an athletic locker room and a weight room. Additionally, ICI performed renovations to exiting spaces that allow for a foods lab, an additional art room as well as relocation of the dance room and expansion of the wrestling room.

The District had a $5.5 million budget for the project. Upon developing an initial cost estimate during the preconstruction phase, ICI projected the cost to be closer to $6.2 million. As such, FGM and ICI worked together with the District to bring the project within budget parameters and the project was successfully completed on budget.